Purpose
RIBA Stage 2 Concept Design marks the transition from feasibility-level cost assessment to structured, elemental cost planning. The design team develops the architectural concept, structural strategy and building services approach, generating sufficient information for the QS to prepare Formal Cost Plan 1 in accordance with RICS NRM 1 (2nd edition, 2012).
The QS role at Stage 2 shifts from order-of-cost estimating to active cost management: establishing elemental cost targets benchmarked against BCIS data, initiating the project Risk Register, providing an early Life Cycle Costing assessment, preparing the initial Cash Flow Forecast, and supporting the Value Engineering review. Cost Plan 1 becomes the formal cost baseline against which all subsequent design development is measured.
This guidance note introduces the QS obligations at RIBA Stage 2, the five principal deliverables (Cost Plan 1, Risk Register, LCC assessment, Cash Flow Forecast and VE support), and the RICS professional standards that govern practice throughout this stage.
Key Principles
- NRM 1: RICS New Rules of Measurement — Order of Cost Estimating and Cost Planning (2nd edition, 2012, effective January 2013): mandatory framework for Formal Cost Plan 1 preparation.
- BCIS Elemental Standard Form of Cost Analysis (SFCA, 4th edition): defines consistent elemental categories for benchmarking and cost plan preparation.
- RICS Cost Analysis and Benchmarking (1st edition, 2016): guidance on applying BCIS adjustment factors (TPI, location, specification, size) to benchmark data.
- RICS Whole Life Costing (1st edition, 2016): requires the QS to advise on whole-life cost implications of design decisions from Stage 2 onwards.
- RICS Management of Risk (1st edition, 2020): framework for establishing the project Risk Register and quantifying cost risk using probability × impact (EMV) methodology.
- RIBA Plan of Work 2020 — Stage 2 Concept Design: defines stage deliverables, including the cost plan, sustainability assessment and project programme.
- RICS Quantity Surveying and Construction Professional Statement (2021): mandatory obligations for QS firms providing cost management services.
Practical Application
Common Mistakes to Avoid
- Failing to reconcile Cost Plan 1 with the Stage 1 OCE — any cost movement must be explained and formally accepted by the client before progressing to Stage 3.
- Issuing Cost Plan 1 without a full assumptions register — undocumented assumptions create significant dispute risk at later stages when costs change.
- Conflating design contingency (a percentage uplift covering design development) with risk allowance (an EMV-based sum for identified, quantified risks).
- Omitting whole-life cost considerations — RICS guidance requires LCC advice from Stage 2, even at indicative level, to inform specification choices.
- Not obtaining formal client sign-off on Cost Plan 1 — without written approval, the cost baseline has no authority for change control purposes.
- Treating Value Engineering as optional — VE is most cost-effective at Stage 2; post-Stage 3 design changes carry progressively higher abortive work costs.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Design Economics & Cost Planning (L2) | Life Cycle Costing (L1) | Value Management (L1)
Concept Design Stage Checklist
CPD Learning Outcomes
- Explain the QS role, key deliverables and RICS obligations at RIBA Stage 2 Concept Design.
- Apply NRM 1 elemental structure and BCIS benchmarking to prepare Formal Cost Plan 1.
- Identify the inter-relationship between Cost Plan 1, the Risk Register, the LCC assessment and the Cash Flow Forecast as integrated Stage 2 deliverables.
Further Reading
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012, RICS Books)
- BCIS Elemental Standard Form of Cost Analysis (SFCA, 4th edition, BCIS)
- RICS Cost Analysis and Benchmarking (1st edition, 2016, RICS Books)
- RICS Whole Life Costing (1st edition, 2016, RICS Books)
- RICS Management of Risk (1st edition, 2020, RICS Books)
- RIBA Plan of Work 2020 (RIBA Publishing)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.