Purpose
The Risk Register at RIBA Stage 2 is the first formal, structured risk management document prepared for the project. It translates the risk allowance carried within the Stage 1 Order of Cost Estimate into an itemised, scored register showing each identified risk's probability, financial impact, Expected Monetary Value (EMV), RAG status, risk owner and response strategy.
The QS owns and maintains the cost risk register throughout the project lifecycle, updating it at each RIBA design stage gateway. The register feeds directly into Cost Plan 1: the sum of all risk EMVs constitutes the risk allowance, which is carried as a separate provision distinct from the design contingency. This distinction is fundamental to transparent cost management under RICS professional standards.
The RICS Management of Risk (1st edition, 2020) and NRM 1 Section 3.6 both require the QS to identify, quantify and respond to cost risks in a systematic manner. The Risk Register is the audit document that demonstrates compliance with these obligations.
Key Principles
- RICS Management of Risk (1st edition, 2020): the primary RICS guidance note for risk management methodology in construction, covering risk identification, probability-impact assessment, EMV calculation and response strategies.
- NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012), Section 3.6 — Risk and Contingencies: requires the QS to separate design contingency (for undefined design development) from risk allowance (for identified, quantified risks).
- ISO 31000:2018 — Risk Management: Guidelines: international standard defining risk management principles, framework and process used as the basis for RICS guidance.
- HM Treasury Green Book (2022): mandates quantified risk assessment (QRA) for public sector projects, requiring probability-weighted cost estimates and Monte Carlo analysis for major schemes.
- Construction (Design and Management) Regulations 2015 (CDM 2015): requires design-stage hazard and risk identification — links directly to the design risk register maintained by the Principal Designer.
- RICS Conflict Avoidance and Dispute Resolution (guidance note, 2021): thorough risk documentation reduces the likelihood of disputes arising from unmanaged or unallocated risks.
Practical Application
Common Mistakes to Avoid
- Conflating risk allowance (EMV-based, item-by-item) with design contingency (an overall percentage for undefined design development) — they are distinct provisions with different purposes and must be reported separately.
- Failing to assign a specific, named risk owner to each risk item — without ownership, risks are not actively managed and response strategies are not implemented.
- Using uncalibrated probability and impact scales — inconsistent scoring across risks renders the RAG status meaningless. Agree scales at project inception and apply consistently.
- Treating Red risks as resolved once a mitigation action is identified — risks must be re-scored after mitigation to reflect the residual probability and impact.
- Failing to update the register at each stage gateway — a Stage 2 register that is not reviewed at Stage 3 provides no ongoing audit evidence of risk management.
- Including contractor-held risks in the pre-contract client risk allowance without a clear transfer mechanism — overstates the client's risk exposure and distorts the EMV total.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Design Economics & Cost Planning (L2) | Legal & Regulatory Compliance (L1) | Programming & Planning (L1)
Risk Register Checklist
CPD Learning Outcomes
- Prepare a project cost risk register in RICS-compliant format, applying EMV calculations, calibrated probability-impact scoring and RAG status to identified Stage 2 risks.
- Distinguish between risk allowance (EMV-derived, item by item) and design contingency (percentage-based) in Stage 2 elemental cost planning, and carry each as a correctly identified separate provision.
- Apply the RICS Management of Risk framework to identify, categorise, score, assign ownership and respond to cost risks at RIBA Stage 2 Concept Design.
Further Reading
- RICS Management of Risk (1st edition, 2020, RICS Books)
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012), Section 3.6 (RICS Books)
- ISO 31000:2018 — Risk Management: Guidelines (ISO)
- HM Treasury Green Book: Central Government Guidance on Appraisal and Evaluation (2022, HM Treasury)
- Construction (Design and Management) Regulations 2015 (SI 2015/51, HMSO)
- RICS Conflict Avoidance and Dispute Resolution (guidance note, 2021, RICS)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.