Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
The initial Cash Flow Forecast prepared at RIBA Stage 2 provides the client with an indicative spend profile over the projected construction period. It enables the client to plan capital drawdowns, arrange funding facilities and schedule financial commitments well in advance of construction commencing. At Stage 2, the forecast is based on the Cost Plan 1 budget and an indicative construction programme — it is an order-of-magnitude planning tool, not a contractual payment schedule.
The QS applies S-curve methodology to model the characteristic pattern of construction expenditure: slow mobilisation at commencement, rapid acceleration through the main construction phase, and a tail-off during fit-out, commissioning and snagging. Professional fees, statutory charges and other non-construction costs are phased separately against the wider project programme.
The initial forecast should be reviewed and updated at each RIBA stage gate as the programme develops and contract arrangements are confirmed. The Stage 4 forecast, based on the contractor's accepted tender programme and cash-flow submission, replaces the Stage 2 indicative profile for financial management purposes.
Key Principles
- RICS Cash Flow Forecasting (RICS guidance note, 2014): the primary RICS framework for preparing and presenting construction project cash flow forecasts, including S-curve methodology and fee phasing.
- NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012): Cost Plan 1 provides the total project budget that forms the basis of the Stage 2 forecast.
- BCIS Tender Price Index (TPI) Forecast: BCIS publishes quarterly TPI forecasts used to adjust the cash flow for tender price inflation over the construction period.
- JCT Standard Building Contract (SBC/Q, 2016 edition), Clause 4: defines interim payment provisions — monthly valuations, retention deduction (typically 3–5%) and release conditions — relevant context for post-contract cash flow accuracy.
- RICS Cost Reporting (Professional Statement, 2nd edition): requires the QS to keep the client informed of the overall project financial position, including cash flow, at appropriate intervals.
- VAT Act 1994 and HM Revenue & Customs Construction VAT guidance: VAT at 20% is payable on most construction contracts and must be included in the cash flow where the client cannot recover it.
Practical Application
Common Mistakes to Avoid
- Producing a linear (even-spread) forecast rather than an S-curve profile — this misrepresents the client's funding requirements and may lead to a mismatch between drawdowns and actual expenditure.
- Omitting professional fees from the overall project cash flow — fees represent a significant early expenditure that must be funded alongside construction costs.
- Failing to model retention correctly — omitting retention release at Practical Completion and the end of the Defects Liability Period understates cashflow in the tail of the programme.
- Not stating whether VAT is included or excluded — for clients who cannot recover VAT (e.g. residential developers on exempt sales, many charities), 20% VAT on the construction cost has a material impact on cash requirements.
- Presenting the Stage 2 forecast as a precise financial commitment — the indicative nature, dependence on an unconfirmed programme, and market inflation uncertainty must be clearly communicated.
- Failing to update the cash flow when the programme changes — every programme revision must trigger a corresponding cash flow update.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Programming & Planning (L1) | Commercial Management (L1) | Design Economics & Cost Planning (L2)
Cash Flow Forecast Checklist
CPD Learning Outcomes
- Prepare an initial project cash flow forecast from a Stage 2 elemental cost plan, applying S-curve methodology and correctly phasing preliminaries, retention, fees and external works.
- Identify key cash flow drivers — retention, VAT, inflation and professional fee phasing — and advise clients on their practical impact on funding requirements.
- Advise clients on the limitations and intended use of Stage 2 indicative cash flow forecasts, and the planned evolution through Stages 3 and 4 as programme and contract information develops.
Further Reading
- RICS Cash Flow Forecasting (RICS guidance note, 2014, RICS Books)
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012, RICS Books)
- BCIS Cost Information Service — Tender Price Index Forecast (BCIS Online)
- JCT Standard Building Contract with Quantities (SBC/Q, 2016 edition, Sweet & Maxwell) — Clause 4 Payment provisions
- HM Revenue & Customs: VAT Notice 708 — Buildings and Construction (HMRC, current edition)
- RICS Cost Reporting (Professional Statement, 2nd edition, RICS)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.