Purpose
Adjudication and Arbitration Records are the formal procedural documents generated during dispute resolution proceedings — Notices of Adjudication, Referral Notices, Responses, Decisions, arbitration submissions, awards, and all associated correspondence and evidence bundles. Maintaining a complete and accurately organised record of all proceedings is essential: for enforcing decisions, for understanding what has and has not been decided (and therefore what remains open), for managing serial adjudications, and for advising clients on their rights following a decision.
Statutory adjudication under HGCRA 1996 is the most commonly used dispute resolution mechanism in English construction disputes. RICS Conflict Avoidance and Dispute Resolution (2024) confirms that every RICS member must understand the adjudication process, its timetable, and the effect of an adjudicator's decision. Adjudication decisions are immediately binding and enforceable in court — even if the decision is subsequently challenged in arbitration or litigation.
Arbitration under the Arbitration Act 1996 produces a final, binding, private award that is generally enforceable in all jurisdictions worldwide (under the New York Convention 1958). The QS must understand the key differences between adjudication (interim, 28-day process, challengeable) and arbitration (final, potentially months-long process, very limited appeal rights) to advise clients correctly on which route to pursue.
Key Principles
- HGCRA 1996, Section 108: right to refer any dispute to adjudication at any time; the adjudicator has 28 days from Referral Notice (42 days with referring party's consent) to reach a decision; the decision is binding until finally determined by arbitration, litigation, or agreement.
- Adjudication enforcement: an adjudicator's decision can be enforced by summary judgment in the TCC; the court will enforce even a decision that may contain errors (Macob Civil Engineering v Morrison Construction [1999]); the only defences are natural justice/jurisdiction challenges.
- Arbitration Act 1996: arbitration requires a written agreement; the arbitrator's award is final and binding; appeals are severely restricted (Sections 68 and 69 — serious irregularity or question of law); the award is private and confidential.
- Serial adjudication: a party may commence multiple adjudications on different aspects of the same dispute (subject to not re-opening the same issue that has already been decided); the QS must track the scope of each adjudication carefully to avoid res judicata (issue already decided) challenges.
- Natural justice in adjudication: the adjudicator must act fairly and not breach the rules of natural justice; common grounds for natural justice challenge include failure to consider all evidence submitted and apparent bias.
- Costs in adjudication: each party generally bears its own costs in adjudication (HGCRA); the adjudicator may award costs only if the contract expressly so provides or if the parties agree.
Practical Application
Common Mistakes to Avoid
- Failing to comply immediately with an adjudicator's decision even while intending to challenge it — the decision is immediately binding and enforceable by summary judgment; non-compliance exposes the client to enforcement proceedings and potential wasted costs.
- Missing the 7-day deadline for serving the Referral Notice after the Notice of Adjudication — the appointment of the adjudicator is linked to the Referral Notice; failure to serve in time can allow the adjudicator's appointment to lapse.
- Failing to raise jurisdictional challenges at the outset of adjudication — a party that participates in adjudication without raising jurisdictional challenges at the start may be taken to have waived those challenges.
- Re-referring a dispute that has already been decided in a previous adjudication — res judicata or issue estoppel may apply; the QS must track what has been decided in previous adjudications before commencing a new one.
- Poor indexing of the evidence bundle in the Referral Notice or Response — adjudicators work to very tight timescales; a disorganised bundle is at risk of having key evidence overlooked.
APC Competency & Quick Reference
- Conflict Avoidance, Management and Dispute Resolution Procedures Level 3 — adjudication procedure, HGCRA, enforcement, arbitration
- Contract Practice Level 2 — contractual dispute resolution provisions, HGCRA rights, natural justice
Dispute & Claims Checklist
CPD Learning Outcomes
- Manage the procedural requirements of a statutory adjudication — Notice of Adjudication, Referral Notice, Response, Decision — within HGCRA 1996 timetables, and advise clients on enforcement and challenge options.
- Distinguish between adjudication (interim, 28-day, challengeable) and arbitration (final, binding, internationally enforceable) and advise clients on the appropriate route for different types of construction dispute.
- Maintain complete adjudication and arbitration records, tracking issues decided in previous proceedings to avoid res judicata challenges in subsequent adjudications or arbitrations.
Further Reading
- RICS, Conflict Avoidance and Dispute Resolution in Construction, 1st edition, April 2012 (reissued August 2024)
- Housing Grants, Construction and Regeneration Act 1996 (as amended 2009) — Section 108 (adjudication)
- Arbitration Act 1996 — Sections 68 (serious irregularity) and 69 (question of law)
- Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] BLR 93 — adjudication enforcement
- RICS, Damages for Delay to Completion, 2nd edition, April 2024
- Technology and Construction Court Guide (TCC Guide) — enforcement of adjudicators' decisions
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.