Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
Completion Assessment is the formal process by which the Contract Administrator and the QS determine whether the works have reached a state sufficiently complete to justify the issue of the Certificate of Practical Completion (CPC). The QS's role is advisory and financial: assessing the outstanding items, advising on the contractual implications of any premature or delayed certification, and ensuring that all associated financial transactions are triggered correctly and on time.
Under English law and RICS guidance, 'practical completion' has no single statutory definition but is established through case law. RICS Defining Completion of Construction Works (1st ed., August 2024) consolidates the principles from key cases including Hoenig v Isaacs [1952] and Jarvis v Westminster Corporation [1970], establishing that PC is reached when the works are complete for all practical purposes — minor snagging does not prevent PC but the existence of known material defects at the time of certification may undermine the certificate.
Correct and timely PC certification is critical: the PC date determines when LADs cease, when the first moiety of retention is released, when the DLP commences, and when the contractor's obligation to insure the works ends. Errors in the PC date have direct financial consequences for the client.
Key Principles
- RICS Defining Completion of Construction Works (1st ed., August 2024): PC is the state in which the works are complete for all practical purposes; sectional completion is valid where the contract provides for it; partial possession does not equate to PC.
- JCT SBC/Q 2016 Clause 2.30: the CA certifies PC when the works are practically complete; Clause 2.32 allows the employer to take partial possession of any part of the works, triggering pro-rata retention release.
- Case law — Hoenig v Isaacs [1952]: substantial performance sufficient for the main contract sum to be due; Jarvis v Westminster [1970]: trivial defects do not prevent PC. PC cannot be withheld for trivial snagging.
- RICS Defects and Rectification (2nd ed.): distinguishes patent defects (visible at inspection), latent defects (hidden, discoverable within the limitation period), and design defects; each has different liability and remedies.
- NEC4 Clause 30.2: the Project Manager certifies Completion within one week of the Contractor achieving it; Completion is defined in the Works Information/Scope. Under NEC4 Clause 35, the Employer may take over any part before Completion.
- HGCRA 1996 (as amended): once PC is certified, the first moiety of retention becomes due; the QS must issue a payment notice within 5 days (JCT Clause 4.9) to avoid the sum becoming the payer's notice by default.
Practical Application
Common Mistakes to Avoid
- Advising the CA to withhold PC because of minor snagging — this can expose the employer to unliquidated damages claims from the contractor for the period beyond the contractual completion date.
- Failing to confirm the PC date in writing immediately after the inspection — ambiguity about the PC date creates LAD calculation disputes and retention release disputes.
- Overlooking the distinction between sectional and overall completion — PC for one section does not trigger events for others; each section's retention and DLP must be tracked independently.
- Failing to issue the payment notice for the first moiety retention release promptly — under HGCRA, a failure to issue a Payment Notice within 5 days (JCT Clause 4.9) means the contractor's application becomes the notified sum by default.
- Treating partial possession (Clause 2.32) and practical completion as equivalent — partial possession is a financial event but not a completion event; the DLP for the part still runs from the partial possession date.
APC Competency & Quick Reference
- Contract Practice Level 3 — advising on Practical Completion, sectional completion, partial possession, and associated retention/LAD implications
- Legal and Regulatory Compliance Level 2 — understanding of case law on PC, HGCRA payment obligations
Completion & Final Account Checklist
CPD Learning Outcomes
- Apply the legal and RICS principles of Practical Completion to advise the Contract Administrator and client on completion certification decisions and their financial consequences.
- Calculate and instruct the first moiety retention release in compliance with HGCRA 1996 and JCT SBC/Q 2016 payment notice requirements.
- Distinguish between patent, latent, and design defects and advise on the appropriate contractual and legal remedies for each category.
Further Reading
- RICS, Defining Completion of Construction Works, 1st edition, August 2024
- RICS, Defects and Rectification, 2nd edition (Black Book)
- JCT Standard Building Contract with Quantities 2016 — Clauses 2.30–2.32, 2.38–2.40, 4.20
- NEC4 Engineering and Construction Contract — Clauses 30.2, 35
- Hoenig v Isaacs [1952] 2 All ER 176; Jarvis v Westminster Corporation [1970] 1 WLR 637
- RICS, Retention, GN 90/2012 — retention release at PC
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.