GN-FE-05

Procurement Route Options

1.1 — April 2026Review April 2027RICS-regulated QS firms (England & Wales)

Purpose

The choice of procurement route is one of the most consequential decisions on any construction project. It determines the allocation of risk between client and contractor, the degree of cost certainty achievable before construction starts, the level of design control retained by the client, the integration of the design and construction teams, and the total programme from brief to completion. Once the route has been acted upon — through appointment of a design team, issue of tender documents, or contractor engagement — it is extremely difficult and expensive to reverse.

The QS’s role at feasibility stage is to prepare a structured procurement strategy and options appraisal, setting out the principal routes available, their advantages and disadvantages relative to the client’s specific priorities for time, cost, quality, risk and performance, and a written recommendation. The governing RICS publication is Developing a Construction Procurement Strategy and Selecting an Appropriate Route (RICS practice information, UK, 2nd edition, August 2024). Tendering and contract selection sit outside this publication and are addressed in separate RICS guidance. For public sector clients, the Procurement Act 2023 (effective February 2025) and sector-specific frameworks such as NHS Procure 23 impose additional statutory and policy obligations.

The client’s decision on procurement route must be recorded in writing. It is not sufficient to discuss options in a meeting and proceed informally. The QS’s written recommendation, and the client’s written acceptance, form part of the project audit trail and will be scrutinised in any subsequent dispute or professional review. Under RICS practice information, the chosen route should also be reviewed at key project milestones (for example, on grant of planning permission or before the construction contract is let) to confirm that the original rationale still holds.

Key Principles

  • Principal procurement routes in UK construction (per RICS practice information, August 2024): (1) Traditional (lump sum) — sequential design-bid-build; client retains design risk; high cost certainty at tender. (2) Traditional (remeasurement / measure-and-value) — priced on a schedule of rates or approximate quantities; used where full scope cannot be defined at tender (e.g. civil engineering, refurbishment with unknown extent). (3) Design and Build (including ‘develop and construct’ and novation variants) — single-point responsibility for design and construction; earlier cost certainty; reduced client design control. (4) Construction Management — works let as separate trade packages direct with the client; construction manager engaged as fee-earning professional; client retains risk. (5) Management Contracting — management contractor holds all works-contractor appointments for a fee on top of works cost; design/construction overlap. (6) Partnering — a collaborative overlay (not a route in itself) applied to project or strategic (multi-project) relationships; negotiation replaces competitive tendering. (7) Public Private Partnerships (PPP/PFI) — long-term concession (typically 25–30 years) delivered through a Special Purpose Vehicle, often including life-cycle and soft FM services. Each route distributes risk, design responsibility, cost certainty and programme differently; none is universally ‘best’.
  • Primary selection criteria: the RICS model prioritises the interplay of time, cost (price certainty) and performance (quality), assessed against the client’s attitude to risk. Supporting criteria include: design control and the desired level of client involvement; client experience and in-house resource; project size, complexity and ‘novelty’ factor; site characteristics; market conditions, including contractor appetite, specialist availability and inflation; whole-life (capital versus operational) cost; and any statutory, funding or accountability obligations. A best-fit solution should be identified, not the most obvious one.
  • Design and Build — fitness for purpose and Employer’s Requirements: a D&B contractor may carry a fitness-for-purpose obligation (a significantly higher duty than the ‘reasonable skill and care’ standard applicable to a designer under a traditional route). Many standard D&B forms expressly exclude fitness-for-purpose, so the contract wording must be checked. The Employer’s Requirements (ERs) document is the load-bearing control — it must be clear, complete and unambiguous, and the contract should state that the ERs prevail over the Contractor’s Proposals in the event of discrepancy. Novation of the design team from client to contractor does not eliminate specification-erosion risk: the design team’s duty of care is transferred, creating a potential conflict of interest. Insurance cover for fitness-for-purpose must be verified (see RICS Risk, liability and insurance).
  • Two-stage tendering: a widely-used variant (applicable to both Traditional and D&B) under which a preferred contractor is appointed at Stage 1 on preliminaries, overheads and profit (and sometimes key subcontract rates), allowing early contractor involvement in buildability and programming. At Stage 2 the subcontract and supply-chain packages are priced to agree the lump sum. The QS’s role at Stage 2 is critical: benchmarking returns, challenging unreasonable rates, and independently validating the final sum. Two-stage is appropriate when design is not complete enough for single-stage competition, programme pressure demands early contractor input, or the contractor market is constrained.
  • Risk: identification, allocation and pricing. Risks should be categorised (typically strategic — e.g. planning, funding; external — political/economic/legislative change; project — cost or programme overrun; and discovery — ground conditions, asbestos) and allocated to the party best able to manage them. Risks that are transferred to the contractor attract a risk premium, which may be uneconomic relative to the probability and impact of the risk. The procurement route should be selected with a clear awareness of the likelihood and severity of risk events.
  • Project Execution Plan (PEP): the PEP is the primary operational document that carries the procurement decision into delivery. It records the chosen route and underlying rationale, the methods for selecting design and construction teams, project control mechanisms, the time schedule, budget, lines of responsibility, handover and evaluation procedures, and identified risks. The PEP is normally prepared by the project manager but should be informed by, and reference, the QS’s procurement recommendation.
  • Client statutory duties and accountability: clients have significant statutory responsibilities — notably under the Construction (Design and Management) Regulations 2015 and the Building Safety Act 2022 (and the wider in-scope regime for higher-risk buildings). The QS should make the client aware of these duties and, where appropriate, help ensure they are discharged. Public sector procurement must comply with the Procurement Act 2023 (effective February 2025), including transparency, supplier registration via Find a Tender, contract pipeline publication and the debarment register. Sector schemes such as NHS Procure 23 may also apply. Value management techniques, whole-life cost assessment and sustainability considerations (particularly for public sector works) should inform the procurement strategy.
  • Contract form is a downstream decision: NEC4 and JCT 2024 are the two principal standard form families used in England & Wales (JCT dominant on building, NEC prevalent on infrastructure and public sector). The contract form follows procurement-route selection but should be flagged in the recommendation so the client can seek legal advice. The QS’s recommendation should also identify the form family, any proposed bespoke amendments, and recommend legal review where amendments are material.

Practical Application

Follow these steps to prepare a procurement strategy and options appraisal at feasibility stage:

Step 1
Establish the client’s primary objectives and risk appetite. Hold a structured discussion with the client, project manager and wider stakeholders (including future users where relevant) to confirm: (a) the relative weight of time, cost (price certainty) and performance (quality) against the business case; (b) fixed programme constraints or completion milestones; (c) the client’s appetite for design control post-contract; (d) capacity to manage construction and design risk in-house; (e) whole-life cost and sustainability priorities; (f) accountability requirements (public funding, audit, parent company); (g) statutory procurement obligations (Procurement Act 2023, sector schemes such as NHS Procure 23). Record the client’s stated priorities in writing and consider formal value management workshops where objectives are complex or contested.
Step 2
Review market conditions and project characteristics. Assess: contractor appetite for the project type and value in the current market; availability of specialist subcontractors and trades; lead times for long-procurement items (structural steel, M&E plant, façades, cladding); tender price inflation; and current competition levels. Consider project size, complexity, site conditions and any ‘novelty’ factor (refurbishment of operational assets, unknown ground conditions, asbestos risk) — these affect which routes are viable and the realistic level of cost certainty.
Step 3
Identify and categorise risks. Working with the project team, record strategic risks (planning, funding), external risks (legislative, environmental, economic), project risks (cost/programme overrun, design change) and discovery risks (ground conditions, existing structures). Assess likelihood and impact. Allocate each risk to the party best able to manage it. Note the premium implied by transferring each significant risk to the contractor — retaining a manageable risk is often cheaper than pricing it out.
Step 4
Prepare the procurement options matrix. For each viable route (Traditional lump sum, Traditional remeasurement, Design & Build, Two-Stage, Construction Management, Management Contracting, and — where relevant — Partnering overlay or PPP/PFI), assess performance against the client’s prioritised criteria: cost certainty, programme, design control, risk allocation, whole-life cost, and market suitability. Use a structured scoring matrix (High / Medium / Low or 1–3 scale) with a brief narrative for each route explaining the score. Highlight routes that are plainly inappropriate and those offering the best fit.
Step 5
Identify the contract form family. For the recommended procurement route, identify the appropriate standard form: JCT 2024 (SBC/Q, DB, MC, CM, Intermediate or Minor Works variants) or NEC4 (ECC Options A–F, or ECSC for smaller works). Note any bespoke amendments proposed by the client, the implications for risk allocation and payment mechanisms, and flag where legal review is required. For D&B, confirm the position on fitness-for-purpose, the quality and completeness of the draft Employer’s Requirements, and whether the design team will be novated.
Step 6
Issue a written procurement recommendation. State clearly: (a) the recommended route and the rationale against the client’s stated objectives; (b) the recommended contract form family; (c) the principal advantages for this specific project; (d) the residual risks and limitations the client accepts by choosing it; (e) the key preconditions for the route to succeed (e.g. design completeness at tender for Traditional; brief/ER fixity at Stage 2 for D&B; client resource capability for Construction Management); (f) any statutory compliance points (Procurement Act 2023, CDM 2015, Building Safety Act 2022). Do not hedge — make a clear, reasoned recommendation.
Step 7
Present the appraisal to the client and project team. Walk through the options matrix and the recommendation. Address questions. If the client elects a different route from the one recommended, record this in writing with the QS’s advice noted, and obtain the client’s written instruction to proceed on the chosen basis.
Step 8
File the procurement recommendation and feed into the Project Execution Plan. The signed or acknowledged procurement recommendation forms part of the project audit trail and should be reflected in the PEP. Update the project programme to include the procurement timeline (tender preparation, tender period, evaluation, appointment). Schedule a review of the chosen route at key milestones — typically on grant of planning permission and before the main construction contract is let — to confirm that the rationale still holds; alternative routes may become more appropriate if circumstances change.

Common Mistakes to Avoid

  • Generic, non-project-specific recommendations. A report that describes the features of Traditional and D&B without applying them to the client’s priorities, programme and risk profile does not discharge the QS’s advisory duty. The recommendation must explicitly tie each route’s characteristics to the client’s weighted objectives.
  • Conflating Construction Management with Management Contracting. These are distinct routes with different contractual structures: under CM the client contracts directly with each trade contractor; under MC the management contractor holds those appointments. The risk profile, cash-flow impact and administrative burden differ materially. Advising on one while meaning the other is a material error.
  • Recommending Design and Build without addressing design control, fitness-for-purpose and ER quality. Clients who expect to retain the same design influence as under Traditional procurement are frequently disappointed. The risks of specification erosion through contractor value engineering, the position on fitness-for-purpose (and associated insurance), and the need for a clear and unambiguous Employer’s Requirements document must be explained and recorded.
  • Ignoring current market conditions and ‘novelty’ factors. A recommendation that does not account for contractor appetite, competition, specialist lead times, tender inflation or unusual project characteristics (refurbishment, listed buildings, poor ground) may be technically correct but practically undeliverable.
  • Failing to record the client’s decision — or to review the route at key milestones. The procurement decision is among the most consequential on the project. Where the client overrides the QS’s recommendation, the override and the advice given must be documented. The chosen route should also be revisited at planning approval and before contract let, to confirm the original rationale still holds; this review is a specific recommendation of RICS practice information.
  • Confusing procurement route with contract form. The route (Traditional, D&B, Two-Stage, CM, MC, PPP) and the contract form (JCT SBC/Q, JCT DB, NEC4 ECC Option A–F) are related but separate decisions. The QS should identify the contract family in the recommendation but not present it as interchangeable with the route.
  • Overlooking client statutory and public procurement obligations. Clients hold significant duties under CDM 2015 and the Building Safety Act 2022. Public sector procurement above threshold must comply with the Procurement Act 2023 (effective February 2025). Advising a public body to use a non-compliant approach exposes both the client and the QS to legal and reputational risk.

APC Competency & Quick Reference

This topic is relevant to: Procurement and Tendering (, Levels 1–3); Contract Practice (, Levels 1–2); Risk Management (, Levels 1–2); Client Care (B2, Levels 1–2); Project Administration (, Level 1) where procurement advice is integrated with the Project Execution Plan.

What criteria should a QS assess when recommending a procurement route?
The RICS model starts from the balance of time, cost (price certainty) and performance (quality), measured against the client’s attitude to risk and the relative importance of each objective in the business case. Supporting criteria include: design control and client involvement; client experience and in-house resource; project size, complexity, novelty and site characteristics; market conditions (contractor appetite, specialist availability, inflation); whole-life versus capital cost; sustainability; statutory obligations (Procurement Act 2023, CDM 2015, Building Safety Act 2022); and accountability requirements. The route chosen should be the ‘best fit’, not the most obvious one, and should be reviewed at key milestones (e.g. planning, pre-contract).
How does Construction Management differ from Management Contracting?
Under Construction Management, the client holds direct contracts with each trade contractor and the construction manager acts as a fee-earning professional co-ordinating design and trade packages — the client retains construction and cash-flow risk and needs an informed, pro-active in-house capability. Under Management Contracting, the management contractor holds all works-contractor appointments and is paid a fee on top of the works cost; there is no contractual link between the client and the works contractors. Both routes overlap design and construction (‘fast track’) and neither offers price certainty until late in the programme; both rely on strong design-team discipline and an experienced QS to produce cost estimates and a cost plan. The choice between them turns on how much contractual risk the client wishes to hold directly and the client’s commercial/administrative capability.
What are the implications of Design and Build for design control, fitness-for-purpose and the Employer’s Requirements?
D&B gives single-point responsibility and earlier cost certainty, but transfers design responsibility to the contractor. A D&B contractor may carry a fitness-for-purpose duty — a higher obligation than the ‘reasonable skill and care’ duty of a designer — but many standard forms exclude it, so the contract wording must be checked and insurance verified. The Employer’s Requirements document is the principal safeguard: it must be clear, complete and unambiguous, and the contract should state that ERs prevail over Contractor’s Proposals in the event of discrepancy. Where the design team is novated, their duty of care transfers to the contractor, creating a potential conflict of interest; client-side design monitoring (e.g. via a client-retained consultant) is often prudent to manage specification-erosion risk from contractor value engineering.

Feasibility Stage Checklist

Client primary objectives recorded in writing — weighting of time, cost (price certainty) and performance (quality), plus design control, risk appetite and whole-life cost priorities
Value management / brief-validation exercise considered (and undertaken where appropriate) to test the client’s objectives against the business case
Market conditions assessed — contractor appetite, tender inflation, specialist/trade availability, lead times for long-procurement items
Risk register prepared — strategic, external, project and discovery risks identified, allocated and priced; residual risk premium recorded
Procurement options matrix prepared — all viable routes (Traditional lump sum, Traditional remeasurement, D&B, Two-Stage, CM, MC, Partnering overlay, PPP/PFI where relevant) scored against client criteria
Public procurement and statutory compliance confirmed — Procurement Act 2023 (effective February 2025), CDM 2015, Building Safety Act 2022, sector schemes (e.g. NHS Procure 23)
Contract form family identified for the recommended route (JCT 2024 or NEC4 variant); bespoke amendments flagged for legal review; fitness-for-purpose position confirmed for D&B
Written procurement recommendation issued — route, rationale, contract form, advantages, residual risks, preconditions for success, and statutory compliance points
Client’s decision recorded in writing, including any override of the QS’s recommendation and the advice given
Procurement timeline and decision fed into the Project Execution Plan; review of the chosen route scheduled for planning approval and pre-contract-let milestones

CPD Learning Outcomes

  • Identify the principal UK procurement routes (Traditional lump sum and remeasurement, Design and Build including novation, Two-Stage, Construction Management, Management Contracting, Partnering, Public Private Partnerships) and explain how each allocates time, cost, quality and risk between the client and contractor.
  • Apply a structured procurement options appraisal against a client’s prioritised objectives, including risk categorisation and allocation, market-condition assessment, whole-life cost considerations, and the statutory obligations arising under the Procurement Act 2023, CDM 2015 and the Building Safety Act 2022.
  • Produce a written, project-specific procurement recommendation that states the recommended route and contract form family, rationale, residual risks, preconditions for success and statutory compliance points; feed the recommendation into the Project Execution Plan; and review the route at key project milestones.

Further Reading

  • RICS Developing a Construction Procurement Strategy and Selecting an Appropriate Route (RICS practice information, UK, 2nd edition, August 2024)
  • RICS Tendering Strategies (2nd edition)
  • RICS Risk, liability and insurance (RICS guidance)
  • RICS Management of Risk (1st edition, reissued as practice information March 2025)
  • JCT Standard Building Contract with Quantities (SBC/Q) 2024 edition and JCT Design and Build Contract 2024
  • NEC4 Engineering and Construction Contract (ECC) Options A–F (2017, with June 2022 amendments)
  • Procurement Act 2023 (effective February 2025) — Cabinet Office guidance; NHS Procure 23
  • Construction (Design and Management) Regulations 2015; Building Safety Act 2022 (HRB regime)
Subscriber Content

Sections 3–8 are for subscribers

Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.