Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
Before a building contract can be safely executed, the QS must confirm that all required insurance, bond and warranty documents are in place or will be provided within the contractually specified timescale. These documents protect the employer against the financial consequences of contractor default, insolvency, defective workmanship, third-party liability and design failure. Proceeding to construction without confirmed insurance and security arrangements is a significant risk management failure that may leave the employer unprotected.
RICS Construction Security and Performance Documents (1st edition, 2013) identifies six categories of construction security document: performance bonds, advance payment bonds, retention bonds, parent company guarantees, collateral warranties, and payment security methods (escrow accounts, project bank accounts). Each serves a distinct purpose in the security framework, and the combination required for any project depends on the contract type, the client's risk appetite, and the contractor's financial standing.
Insurances — particularly the contractor's All Risks policy, public liability cover, and (for D&B) professional indemnity insurance — must be in force from the date of contract execution. Failure by the contractor to maintain required insurances is a breach of contract entitling the employer to take out insurance at the contractor's cost under most standard forms.
Key Principles
- RICS Construction Security and Performance Documents (1st edition, 2013): defines and explains performance bonds, advance payment bonds, retention bonds, parent company guarantees, collateral warranties, third-party rights, direct agreements and payment security methods.
- JCT SBC/Q 2016, Schedule 3 — Insurance Options: three insurance options — Option A (contractor insures all risks); Option B (employer insures all risks); Option C (existing structures — employer insures). Most new-build contracts use Option A.
- Performance bonds: conditional/default bond; financial limit typically up to 10% of the contract sum; payable on proven contractor default. On-demand bonds (more common in international/PPP projects) are payable without proof of default.
- Collateral warranties: provide third-party beneficiaries (funders, purchasers, tenants) with a direct contractual right against design consultants and the main contractor. Each warranty must be executed before the beneficiary's interest is at risk (typically before practical completion for purchaser/tenant warranties; before drawdown for funder warranties).
- Contracts (Rights of Third Parties) Act 1999: alternative to collateral warranties; allows beneficiaries named in the contract to enforce specific provisions without a separate warranty; increasingly adopted in NEC4 contracts.
- Project bank accounts (PBAs): joint employer/contractor account; employer pays construction certificates directly into the PBA; funds distributed to supply chain on payment due dates; monies held on trust, protected against contractor insolvency; increasingly required on public sector contracts.
Practical Application
Common Mistakes to Avoid
- Executing the contract before performance bond and insurance certificates are received — the contract may require these to be provided before or on execution; failure to obtain them leaves the employer unprotected from day one.
- Accepting a performance bond from an unrated or non-FCA regulated insurer — a bond is only as good as the financial strength of the bondsman; an unrated bondsman's bond may be worthless in the event of contractor default.
- Not confirming the retroactive date on D&B contractor's PI insurance — a policy without an adequate retroactive date will not cover design work carried out before the policy inception date, creating an uninsured design liability gap.
- Forgetting to execute collateral warranties for funders before the first drawdown — a funder whose security interest precedes the practical completion date needs warranties executed before their funds are at risk, not after.
- Not retaining original executed warranty documents — originals are essential evidence of the warranty's existence and terms; copies are insufficient for enforcement purposes.
- Accepting insurance certificates at face value without verification — where any doubt exists about a policy's validity, scope of cover, sum insured or renewal status, verify directly with the insurer rather than relying on the contractor's broker summary. Forged, lapsed or under-limit certificates are a recurrent source of professional liability exposure.
APC Competency & Quick Reference
APC Competencies: Legal & Regulatory Compliance (L2) | Cost Management (L1) | Procurement & Tendering (L2) | Contract Administration (L1)
Insurances, Bonds & Warranties Checklist
CPD Learning Outcomes
- Review and confirm the insurance, bond, and warranty requirements for a building contract against the RICS Construction Security and Performance Documents framework, identifying the purpose and legal structure of each document type.
- Distinguish between conditional/default performance bonds and on-demand bonds, and between collateral warranties and third-party rights under the Contracts (Rights of Third Parties) Act 1999, advising clients on the appropriate protection for each project context.
- Describe the operation of a project bank account, its trust status, and its role in protecting supply chain payments against contractor insolvency.
Further Reading
- RICS Construction Security and Performance Documents (1st edition, 2013, RICS Books)
- JCT Standard Building Contract with Quantities (SBC/Q, 2016 edition) — Schedule 3 Insurance Options
- JCT Design and Build Contract (DB, 2016 edition, Sweet & Maxwell)
- Contracts (Rights of Third Parties) Act 1999 (c.31, HMSO)
- Employers' Liability (Compulsory Insurance) Act 1969 (c.57, HMSO)
- NEC4 Engineering and Construction Contract (2017, Thomas Telford) — Option Y(UK)2 (project bank accounts)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.