Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
Construction contracts impose strict requirements on when and how contractual notices must be served. Failure to serve a notice within the prescribed time limit — or failure to serve it at all — can forfeit the serving party's right to a remedy, even where the underlying entitlement is clear and well-evidenced. The QS must understand the notice requirements of the contract form being used, maintain a notices register throughout Stage 5, and advise the CA/PM and client on compliance proactively — not retrospectively.
The QS's role in contractual notices and claims management spans four key areas: (1) advising the CA/PM on whether the contractor's notices are validly served and within time; (2) assessing the merits of EoT applications and L&E claims and advising on appropriate responses; (3) administering the employer's own notices (Pay Less Notices, LAD deduction notices, acceleration instructions); and (4) ensuring all assessed claims are reflected in the Forecast Final Cost so that the client's budget position is accurately reported.
RICS Extensions of Time (1st edition, effective 10 February 2015) and RICS Ascertaining Loss and Expense (2nd edition, July 2024) are the primary reference documents. They must be read alongside the specific contract form: a Relevant Event under JCT SBC/Q gives the contractor EoT entitlement but does not automatically give L&E entitlement — only a Relevant Matter does both.
Key Principles
- RICS Extensions of Time (1st edition, effective 10 February 2015): definition of Relevant Events (JCT) and Compensation Events (NEC4); EoT assessment methodology; concurrency (contractor-caused and employer-caused delay overlapping); float — whether programme float belongs to the employer or contractor (JCT: employer; NEC4: shared).
- RICS Ascertaining Loss and Expense (2nd edition, July 2024): Relevant Matters (JCT SBC/Q 2016, Clause 4.21) — the subset of events giving rise to L&E entitlement in addition to EoT; heads of L&E claim (site preliminaries, labour inefficiency, finance charges, head office overheads); evidence requirements; Emden/Hudson formula for HOOH claims.
- RICS Damages for Delay to Completion (2nd edition, April 2024): LADs — test for validity (genuine pre-estimate of loss; Cavendish Square [2015] UKSC 67 penalty rule); calculation basis; deduction procedure (Pay Less Notice); prevention principle — employer's own default preventing contractor from completing prevents enforcement of LADs (Multiplex v Honeywell [2007]).
- RICS Acceleration (2nd edition, 2024): distinction between acceleration (employer-instructed programme recovery) and mitigation (contractor's duty); constructive acceleration risk — if the employer refuses a valid EoT, the contractor may claim acceleration costs as damages; formal acceleration agreements must set out scope, cost, and programme recovery.
- JCT SBC/Q 2016, Clauses 2.24–2.29 (EoT) and 4.20–4.23 (L&E): contractor must give written notice 'forthwith' when it becomes reasonably apparent that completion will be delayed; CA must grant an EoT 'so soon as is reasonably practicable' and not later than 12 weeks after receipt of sufficient information.
- NEC4 ECC, Clauses 60.1, 61.3 and 62–65: 21 compensation events; eight-week notification time bar; PM's assessment obligation (within 2 weeks of contractor's quotation); deemed acceptance if PM fails to assess in time.
- Contractor insolvency — changes to the notice regime: when a contractor becomes insolvent during Stage 5, the standard contractual notice and payment framework is materially altered and the QS must understand the specific obligations that arise. Under HGCRA 1996 s.111(10), once insolvency is established, the prohibition on 'pay when paid' clauses no longer applies — meaning the employer is no longer required to pay the contractor before the contractor pays its subcontractors; the standard withholding notice requirement under s.111 also changes in an insolvency scenario. However — and critically — a Pay Less Notice IS still required for any payment due date that falls before insolvency is formally confirmed; a QS who stops issuing payment notices prematurely (in anticipation of likely insolvency) risks the full certified sum becoming payable as a default sum under HGCRA. Under JCT SBC/Q 2016 Clause 8.5, certain provisions apply automatically upon contractor insolvency, regardless of whether the employer serves a formal termination notice: no further sums become due to the contractor (Clause 8.5.3) and the employer's obligation to make payments is suspended. If the employer elects to complete the works using a replacement contractor (Clause 8.7), a specific notice is required. The QS must liaise with the client's solicitors immediately on any insolvency event to ensure the correct notices are served and no premature or incorrect payment is made. Cross-reference: GN-FA-00 — Notional Final Account.
Practical Application
Common Mistakes to Avoid
- Missing the NEC4 eight-week compensation event notification time bar — once the time bar has expired, the contractor loses all entitlement; the CA/PM must actively monitor the register of compensation events and prompt the contractor if a notification appears late.
- Confusing Relevant Events with Relevant Matters — a Relevant Event gives EoT entitlement; only a Relevant Matter (a subset of the Relevant Events list) also gives rise to L&E entitlement. Granting an EoT for a Relevant Event that is not a Relevant Matter does not automatically entitle the contractor to loss and expense.
- Not issuing a Pay Less Notice before deducting LADs — a LAD deduction from a payment without a valid, timely Pay Less Notice is a breach of the HGCRA payment obligations; the employer must pay the full certified sum and pursue the LAD deduction separately.
- Accepting head office overhead claims without scrutinising the formula — the Emden formula requires the contractor to demonstrate actual overhead contribution earned during the period; where the contractor's other work absorbed overheads, the Emden formula may overstate the claim.
- Excluding material claims from the FFC pending formal agreement — the cost report must include the QS's best assessment of all likely claims, including those not yet formally agreed; excluding them understates the FFC and misleads the client about the budget position.
- Stopping Payment Notices or Pay Less Notices prematurely when insolvency is suspected but not confirmed — a QS who withholds payment notices in anticipation of likely insolvency (before it is formally established) exposes the employer to an HGCRA breach and a contractor's claim. Payment notices must continue to be issued correctly until the insolvency event is formally confirmed. Equally, do not make any payment to the contractor after the insolvency event without legal advice — under JCT Clause 8.5.3, the employer's obligation to make further payments is suspended upon contractor insolvency.
APC Competency & Quick Reference
- Contract Practice Level 3 — EoT, L&E, LADs, Pay Less Notices, acceleration, insolvency notice provisions
- Conflict Avoidance, Management and Dispute Resolution Procedures Level 2 — claims management, constructive acceleration, prevention principle
- Legal and Regulatory Compliance Level 2 — HGCRA payment notices, s.111(10) insolvency exception, JCT Clause 8 automatic provisions
Contract Notices & Claims Checklist
CPD Learning Outcomes
- Distinguish between Relevant Events (EoT entitlement) and Relevant Matters (L&E entitlement) under JCT SBC/Q 2016, apply the contractual notice requirements for each, and advise the CA/PM on the merits and quantum of contractor claims.
- Apply the NEC4 compensation event notification time bar (Clause 61.3) and advise on the consequences of missed notification, the PM's assessment obligations, and the risk of deemed acceptance.
- Assess loss and expense claims using accepted methodologies (Emden/Hudson formula for head office overheads; time-related preliminaries for prolongation), scrutinise the evidential basis, and include the assessment in the Forecast Final Cost.
- Apply the contractor insolvency notice framework under HGCRA 1996 s.111(10) and JCT SBC/Q 2016 Clause 8.5 — distinguishing the notice obligations before and after formal insolvency confirmation, avoiding premature payment withholding, and ensuring accurate payment records are maintained as the foundation for the Notional Final Account at Stage 6.
Further Reading
- RICS, Extensions of Time, 1st edition, effective 10 February 2015
- RICS, Ascertaining Loss and Expense, 2nd edition, July 2024
- RICS, Damages for Delay to Completion, 2nd edition, April 2024
- RICS, Acceleration, 2nd edition, 2024
- RICS, Termination of Contract, Corporate Recovery and Insolvency, GN 104/2013 — notice obligations upon contractor insolvency
- JCT Standard Building Contract with Quantities 2016 — Clauses 2.24–2.29 (EoT), 4.20–4.23 (L&E), 8.5 and 8.7 (insolvency and termination provisions)
- Housing Grants, Construction and Regeneration Act 1996 (as amended 2009) — s.111(10): insolvency exception to pay-when-paid prohibition
- Cavendish Square Holdings BV v Makdessi; ParkingEye Ltd v Beavis [2015] UKSC 67 — test for penalties vs LADs
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.