Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
The Final Account Forecast (FAF) is the QS's structured estimate of the likely final financial settlement of the contract, prepared at Practical Completion and updated periodically throughout the Defects Liability Period until the Final Account is formally agreed. It is the QS's professional statement of where the project is expected to settle, clearly distinguishing between agreed items, assessed items, disputed items, and anticipated but not yet submitted items.
The FAF is a critical risk management tool for the client. It enables the client to understand the financial exposure at the end of the project, to make informed decisions about disputed items (whether to negotiate, settle commercially, or refer to adjudication), and to report accurately to their own board, funder, or programme manager. Under RICS Project Financial Control and Reporting guidance, the QS must report the FAF honestly and conservatively — inflating 'agreed' items to give a false picture of settlement progress is a professional integrity failure.
The FAF should be presented as a structured schedule with clear status categories for each item, enabling the client and their advisers to see the full range of outcomes from best case (all disputed items resolved in client's favour) to worst case (all disputed items resolved in contractor's favour).
Key Principles
- RICS Final Account Procedures (1st ed.): the QS is required to prepare and present a forecast of the Final Account settlement from PC, updated as items are agreed or positions change.
- RICS Project Financial Control and Reporting: requires cost reports to distinguish clearly between agreed, assessed, disputed, and anticipated items — presenting a realistic, not optimistic, view of the likely settlement.
- JCT SBC/Q 2016 Clause 4.12: the contractor must submit its Final Account within 3 months of PC (or such other period as specified); the QS should request this submission promptly and check it against their own records.
- RICS Ascertaining Loss and Expense (2nd ed., July 2024): provides the methodology for assessing prolongation and disruption claims; the FAF must include a reasoned assessment of all outstanding claims, not merely accept the contractor's figures.
- RICS Change Control and Management (1st ed., effective 1 April 2021): variation register must be updated at PC to reflect the status of all instructions — agreed, unagreed, instructed-not-yet-valued.
- RICS Cost Prediction PS (effective 1 January 2020): the QS must be able to identify and account for all known risk items in cost reporting; the FAF is the final application of this requirement before the account is closed.
Practical Application
Common Mistakes to Avoid
- Presenting only a single 'best estimate' figure without ranges — the client needs to understand the financial risk exposure, not just a central number.
- Categorising assessed items as 'agreed' to make the picture look more settled than it is — this is a professional integrity failure under RICS rules.
- Failing to account for the contractor's known but not-yet-submitted claims in the FAF — anticipated items should be included as a risk allowance, not ignored until submitted.
- Not updating the FAF regularly during the DLP — a stale forecast at the time the Final Account is agreed is a reporting failure.
- Accepting the contractor's Final Account submission without independent verification — the QS must check every item against their own project records before accepting any figure.
APC Competency & Quick Reference
- Project Financial Control and Reporting Level 3 — Final Account Forecast preparation, range reporting, client advice
- Contract Practice Level 3 — contractor's submission obligations, variation status, loss and expense assessment
Completion & Final Account Checklist
CPD Learning Outcomes
- Construct a Final Account Forecast with clearly categorised status items and present a realistic settlement range to the client in compliance with RICS Project Financial Control and Reporting requirements.
- Apply RICS Ascertaining Loss and Expense (2nd ed., July 2024) methodology to assess prolongation and disruption claims for inclusion in the Final Account Forecast.
- Advise clients on the commercial case for negotiated settlement versus adjudication for disputed Final Account items, taking account of the relative costs and risks of each approach.
Further Reading
- RICS, Final Account Procedures, 1st edition (Black Book)
- RICS, Ascertaining Loss and Expense, 2nd edition, July 2024
- RICS, Project Financial Control and Reporting (Black Book)
- RICS, Change Control and Management, 1st edition, effective 1 April 2021
- JCT Standard Building Contract with Quantities 2016 — Clause 4.12 (contractor's Final Account submission)
- RICS, Cost Prediction PS, effective 1 January 2020
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.