Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
Final Account Agreement is the formal process by which the QS and the contractor's QS negotiate and agree the total financial settlement of the construction contract, producing a signed Final Account Statement that records the Adjusted Contract Sum and extinguishes all outstanding financial obligations between the parties (except for those specifically reserved). It is the culmination of the entire variations and claims close-out process and the direct precursor to the issue of the Final Certificate.
The RICS Final Account Procedures (1st ed.) establishes that the Final Account should be prepared by the QS and checked against the contractor's submission; differences should be resolved by negotiation; and unresolved items must be referred to adjudication, arbitration, or litigation before the Final Certificate is issued — not after, since the Final Certificate is conclusive once the 28-day challenge period passes.
The Final Account Agreement is also the document that provides the financial data for the Cost Plan Reconciliation and the Final Cost Report: once the account is agreed, the QS can prepare the definitive reconciliation showing movement from original contract sum to final outturn and the BCIS elemental cost analysis for benchmarking.
Key Principles
- RICS Final Account Procedures (1st ed.): sets out the structured process — contractor's submission, QS checking, queries, negotiation, agreement, and final statement; both parties should sign the Final Account Statement.
- JCT SBC/Q 2016 Clause 4.12–4.15: contractor submits Final Account within 3 months of PC; QS sends Final Statement within 3 months of receipt; Final Certificate is conclusive unless challenged within 28 days (Clause 4.15).
- RICS Ascertaining Loss and Expense (2nd ed., July 2024): the Final Account must include the fully assessed and agreed loss and expense figure — not a 'holding' estimate; the agreed L&E figure must be substantiated.
- JCT SBC/Q 2016 Clause 4.21: interest is payable on unpaid amounts from the Final Date for Payment at the contractual interest rate; the QS must ensure the Final Certificate is issued and paid on time to avoid interest accruing.
- RICS Termination of Contract, Corporate Recovery and Insolvency (2nd edition, 2018): where the contractor is insolvent before the Final Account is agreed, the QS must prepare a Notional Final Account; the insolvency provisions of the contract (JCT Clause 8.5) apply to the settlement of monies due.
- NEC4 Clause 53: the Project Manager's final assessment is binding unless the contractor notifies a dispute within 4 weeks; the dispute resolution procedure then applies.
Practical Application
Common Mistakes to Avoid
- Issuing the Final Certificate without confirming that all disputes are either agreed or formally referred — once the 28-day window passes, the Final Certificate is conclusive and disputed amounts are unrecoverable.
- Accepting the contractor's Final Account submission figures without independent checking — every figure must be verified against the QS's own records and project documentation.
- Failing to obtain client authority before making any concession on disputed items — the QS has no authority to give away the client's money; any settlement above the QS's own assessment requires client sign-off.
- Not signing the Final Account Statement jointly with the contractor — a unilateral QS statement is valid under JCT Clause 4.12 but a jointly signed statement is far stronger evidence of agreement and avoids later disputes.
- Delaying the Final Account Agreement without a clear programme — the longer the agreement is deferred, the harder it becomes; key project personnel leave, records become inaccessible, and disputes entrench.
APC Competency & Quick Reference
- Contract Practice Level 3 — Final Account agreement process, Final Certificate, conclusive certificate risk
- Project Financial Control and Reporting Level 3 — Final Account Statement, client reporting
Completion & Final Account Checklist
CPD Learning Outcomes
- Manage the Final Account Agreement process from the contractor's submission through negotiation to a signed Final Account Statement, in compliance with JCT SBC/Q 2016 Clause 4.12 and RICS Final Account Procedures.
- Advise clients on the conclusive effect of the Final Certificate under JCT Clause 4.15 and ensure all disputes are formally referred before the 28-day challenge window closes.
- Apply the insolvency provisions of JCT Clause 8.5 and RICS Termination of Contract, Corporate Recovery and Insolvency (2nd edition, 2018) to prepare a Notional Final Account where the contractor becomes insolvent.
Further Reading
- RICS, Final Account Procedures (1st edition, 2013, RICS Books — Black Book)
- RICS, Ascertaining Loss and Expense, 2nd edition, July 2024
- RICS, Termination of Contract, Corporate Recovery and Insolvency (2nd edition, 2018, RICS Books)
- JCT Standard Building Contract with Quantities 2016 — Clauses 4.12–4.15, 4.21, 8.5
- NEC4 Engineering and Construction Contract — Clause 53 (final assessment)
- RICS, Retention (1st edition, 2012, RICS Books) — verify for current reissue
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.