Purpose
Benchmarking and cost analysis are the twin disciplines that underpin evidence-based cost advice. Benchmarking is the process of comparing a project’s cost, programme, or performance metrics against equivalent completed projects to test whether the current estimate is realistic and to identify where costs diverge from the norm. Cost analysis is the structured recording, presentation, and interpretation of cost data from completed projects so that it can be used reliably in future estimating.
At feasibility stage, benchmarking provides the evidential foundation for the Order of Cost Estimate. At later stages, it enables the QS to test whether evolving cost plans remain aligned with comparable schemes and to challenge design or specification decisions that are driving costs above reasonable norms. The governing RICS publication is Cost Analysis and Benchmarking (2nd edition), which sets out principles, definitions, and best practice for both activities.
The RICS Elemental Standard Form of Cost Analysis (BCIS NRM Edition) — Principles, Instructions, Elements and Definitions (2012) provides the mandatory format for recording and submitting cost analysis data to BCIS. Firms that submit cost analyses to BCIS contribute to the industry’s shared knowledge base and simultaneously demonstrate the data management rigour expected at APC Level 1 (Data Management, ).
Key Principles
- Cost analysis is structured around the BCIS/NRM 1 elemental breakdown. Elements are standardised categories of building work (substructure, frame, upper floors, roof, external walls, windows and external doors, internal walls and partitions, internal doors, wall finishes, floor finishes, ceiling finishes, fittings and furnishings, sanitary appliances, services, and external works). Using a consistent elemental structure across all projects makes comparisons valid.
- The key cost analysis metrics are: (a) £/m² GIFA — overall and elemental; (b) element unit rate (EUR) — cost per unit of an element (e.g. £/m² of roof area); (c) element unit quantity (EUQ) — the quantity of each element per m² GIFA; (d) proportion of cost — each element’s share of the total measured works cost. Together these allow like-for-like comparison between projects of different sizes.
- The wall-to-floor ratio (W:F ratio) is a key design efficiency metric. It measures the ratio of external wall area to GIFA. A high W:F ratio (e.g. above 0.6) indicates a complex or fragmented building form that drives up external envelope costs. A low ratio (e.g. 0.3–0.4) indicates a compact, efficient form. The W:F ratio is always recorded in a cost analysis and used when comparing projects.
- Abnormal costs must be stripped out of the cost analysis before submitting to BCIS or using for benchmarking. Abnormals — piled foundations, contamination, complex access, listed building, specialist fit-out — are project-specific and would distort the benchmark if included in the elemental rates. They should be recorded separately as an addendum to the analysis.
- BCIS adjustments are always required when using published benchmark data. Location factors, Tender Price Index, and specification adjustments must be applied before comparing or using BCIS data on a new project. Raw BCIS rates are base-date historical figures and cannot be used without adjustment.
- Employer’s consent is required before using project cost data for external benchmarking or publication. Most appointment forms include confidentiality provisions. The QS should check the terms of appointment before submitting data to BCIS or using a project as a comparator in a published or shared context.
- Benchmarking is not just a feasibility tool. It should be applied at every cost plan stage to test the evolving design against comparable schemes. A cost plan that shows a particular element significantly above benchmark warrants investigation — it may reflect a genuine design decision or it may signal an error.
Practical Application
Follow these steps when undertaking benchmarking at feasibility stage and when preparing or submitting a cost analysis on completion of a project:
Common Mistakes to Avoid
- Comparing unadjusted costs. Comparing a 2019 Inner London project with a 2024 South West project without applying TPI and location factor adjustments produces a meaningless result. All comparisons must be on a common base date and location.
- Including abnormals in elemental rates. Piled foundations or complex M&E included in the substructure or services elemental rate will make the rate look high and distort future estimates that use it as a benchmark. Abnormals must always be stripped out and listed separately.
- Using too small a comparator sample. A single ‘similar’ project is not a benchmark — it is anecdote. The QS should draw on at least 10–15 comparators from BCIS or the firm’s cost database to produce a statistically meaningful range.
- Failing to record the W:F ratio and other efficiency metrics. Without these, the cost analysis cannot be meaningfully compared to others. The W:F ratio, GIFA, NIA, number of storeys, and structural frame type are minimum required data points for any analysis.
- Using project cost data for benchmarking without employer’s consent. This is a confidentiality breach. Check the appointment terms before using or sharing project data, even in anonymised form.
- Treating benchmarking as a one-stage exercise. Benchmarking at feasibility is the start of the process, not the end. The QS should apply benchmarking at each cost plan stage to ensure the evolving design remains within normal cost parameters for the building type.
APC Competency & Quick Reference
This guidance note is relevant to the following RICS competencies under the Quantity Surveying and Construction pathway (December 2025): Design economics and cost planning (Levels 1–3); Quantification and costing of construction works (Levels 1–2); Data management (Levels 1–2). Refer to the current RICS Quantity Surveying and Construction Pathway Guide (December 2025) and the RICS APC Candidate Guide (February 2024) for full competency definitions and assessment requirements. See also the RICS Sector pathways page for updates.
Feasibility Stage Checklist
CPD Learning Outcomes
- Prepare a structured elemental cost analysis in accordance with the BCIS/NRM 1 elemental breakdown, calculating cost per m² GIFA, EUQ, EUR, and proportion of measured works for each element.
- Apply location, time, and specification adjustments to benchmark data and conduct a meaningful like-for-like comparison between the subject project and BCIS comparators, identifying and investigating elemental outliers.
- Identify abnormal costs within a project cost analysis, strip them from elemental rates, and record them separately to preserve the integrity of the analysis for future benchmarking use.
Further Reading
- RICS Cost Analysis and Benchmarking (2nd edition)
- BCIS Elemental Standard Form of Cost Analysis (NRM Edition) — Principles, Instructions, Elements and Definitions (RICS, 2012)
- RICS NRM 1: Order of Cost Estimating and Cost Planning for Capital Building Works (2nd edition, reissued as practice information October 2022)
- RICS Cost Prediction Professional Statement, Global (1st edition, reissued June 2024)
- RICS IPMS: International Property Measurement Standards — All Buildings (2nd edition)
- BCIS Online — Building Cost Information Service (RICS) — current subscription data