Purpose
Establishing the cost limit and setting the project budget are among the most consequential tasks the QS performs at feasibility stage. The cost limit is the maximum sum the client is prepared to commit to the project at the point of sanction. The project budget is the QS’s structured allocation of that sum across all cost components — construction works, contingency, fees, statutory costs, inflation, and other development expenditure. Both must be set with rigour, documented in writing, and formally agreed with the client before design proceeds.
NRM 1 (2nd edition, reissued October 2022) defines the cost limit as the authorised budget for the project and prescribes how it must be structured. A cost limit that has been derived from the Order of Cost Estimate, reviewed against benchmark data, and agreed in writing provides the baseline against which all subsequent cost plans are measured. When a cost limit is set informally, or simply taken from the client's hoped-for figure without QS input, it often leads to cost overruns and disputes.
The RICS Cost Prediction Professional Statement (reissued June 2024) requires that any cost prediction communicated to a client — including the recommended budget — is accompanied by a statement of its basis, assumptions, exclusions, and accuracy range. This obligation applies equally to the initial budget recommendation and to any subsequent revision.
Key Principles
- The cost limit is the client’s authorised maximum expenditure. It is set following QS review of the Order of Cost Estimate and must reflect a realistic, evidence-based assessment of the total project cost — not the client’s preferred or aspirational figure. If the client’s stated budget is below the QS’s estimate, this must be reported to the client in writing immediately, with options to resolve the gap (scope reduction, specification change, phasing, or budget increase).
- The NRM 1 cost limit structure separates the project cost into defined components: (1) Construction Works Estimate (measured works + preliminaries + contractor OHP); (2) Project/Design Team Fees; (3) Other Development/Project Costs (statutory, planning, surveys, decant, furniture and equipment); (4) Risk Allowances (design contingency + construction risk); (5) Inflation Allowance; (6) VAT (if applicable and not recoverable). Each component must be separately estimated and documented.
- Contingency and risk allowances are not the same thing and must not be conflated. The design contingency covers the cost of design development and scope growth as the project advances — it reduces as design is resolved. The construction risk allowance covers identified project risks that may or may not crystallise. A general contingency without a defined risk basis is not an acceptable approach under NRM 1.
- The budget must be actively managed, not merely set and filed. The QS’s role is to track actual and committed expenditure against each budget component throughout the project and to report variances promptly. A budget that is set at feasibility and not revisited until practical completion is not cost management — it is cost recording.
- Inflation is a discrete budget component and must not be buried in the construction works estimate. At feasibility stage, the inflation allowance should cover the period from the cost plan base date to the mid-point of the construction programme. The basis for the inflation rate (BCIS TPI forecast, fixed assumption, or other) must be stated.
- Where the client has a fixed or capped funding envelope (e.g. a grant, a board-approved capital allocation, or a development appraisal constraint), the QS must advise explicitly whether the proposed scope is achievable within that envelope. If it is not, the QS must not simply compress the estimate to fit — this creates a false budget and exposes both the client and the firm to significant risk.
Practical Application
Follow these steps to establish a compliant cost limit and structured project budget at feasibility stage:
Common Mistakes to Avoid
- Accepting the client’s aspirational budget as the cost limit without QS review. If the client’s figure is below the OCE, the shortfall must be reported in writing immediately. Proceeding without doing so is a dereliction of the QS’s advisory duty and a likely source of future dispute.
- Conflating design contingency and construction risk allowance. These are separate budget components serving different purposes. Design contingency reduces as design is resolved; construction risk is linked to the risk register. Lumping them together as a single “contingency” line makes the budget opaque and makes monitoring ineffective.
- Burying inflation within the construction works estimate rather than treating it as a discrete budget component. This obscures the inflation assumption, makes it impossible to update it when market conditions change, and understates the construction works cost.
- Failing to confirm which items are excluded from the budget. FF&E, IT, tenant fit-out, section 106/278 obligations, and VAT are commonly excluded. If excluded items are not explicitly listed, the client may assume they are included — and the QS will be held responsible for the shortfall.
- Not obtaining written sign-off on the cost limit. A budget agreed verbally in a meeting is not a budget — it is a conversation. The QS must always issue the budget in writing and obtain written acknowledgement. This is the baseline against which all subsequent cost performance will be measured.
- Setting the budget and then failing to manage it. Budget setting without ongoing cost reporting and proactive variance analysis is a fundamental failure of the QS’s cost management role. The budget must be a living document, reviewed at every project milestone.
APC Competency & Quick Reference
This guidance note is relevant to the following RICS APC competencies: Cost Management (, Levels 1–3); Client Care (B2, Levels 1–2); Risk Management (, Levels 1–2); Financial Management (, Level 1).
Feasibility Stage Checklist
CPD Learning Outcomes
- Build a structured NRM 1 project budget from an Order of Cost Estimate, allocating all cost components — construction works, fees, development costs, contingency, inflation, and VAT — as discrete and documented budget lines.
- Identify and report a gap between the QS’s recommended budget and the client’s funding envelope, presenting costed options to bridge the gap in a format suitable for client decision-making.
- Distinguish between design contingency and construction risk allowance, explain how each is quantified and how each changes as the project advances through the RIBA work stages.
Further Reading
- RICS NRM 1: Order of Cost Estimating and Cost Planning for Capital Building Works (2nd edition, reissued as practice information October 2022)
- RICS Cost Prediction Professional Statement, Global (1st edition, reissued June 2024)
- RICS Value Management and Value Engineering (1st edition)
- RICS Management of Risk (1st edition, reissued as practice information March 2025)
- RICS Cost Analysis and Benchmarking (2nd edition)
- RICS Life Cycle Costing (1st edition, 2016)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.