Purpose
Formal Cost Plan 2 is the Stage 3 elemental cost plan, prepared from the spatially coordinated design produced at RIBA Stage 3. It is materially more robust than Cost Plan 1: it is based on coordinated architectural, structural and M&E drawings, carries measured elemental quantities rather than purely benchmark-derived allocations, and adopts a lower design contingency reflecting the reduced level of design uncertainty compared to Stage 2.
Under the RICS Cost Prediction Professional Statement (1st edition, effective 1 July 2021), Cost Plan 2 must include a cost movement schedule reconciling its total to Cost Plan 1, with all changes categorised and explained. This mandatory requirement ensures full transparency of cost movement from the approved Stage 2 baseline, and gives the client the information needed to either accept the revised position or instruct design changes before Stage 4 commences.
The RICS Cost Analysis and Benchmarking (2nd edition, 2024) guidance is central to Cost Plan 2 preparation: it confirms that the QS must continue to benchmark elemental unit rates against BCIS cost analysis data, applying TPI and location adjustments to ensure the comparison is on a like-for-like basis. Any element still diverging materially from BCIS norms must be flagged for VE review.
Key Principles
- NRM 1: RICS New Rules of Measurement — Order of Cost Estimating and Cost Planning (2nd edition, 2012), Parts 3 and 4: Part 3 defines the measurement rules for cost planning at Stage 3; Part 4 provides tabulated rules for elemental sub-division at a level of detail appropriate to the coordinated design.
- RICS Cost Prediction (Professional Statement, 1st edition, effective 1 July 2021): mandates that cost plan reports state the change from the previous cost plan and the reasons for each change — mandatory, not guidance.
- RICS Cost Analysis and Benchmarking (2nd edition, 2024): framework for benchmarking elemental unit rates against BCIS data; specifies the data to record in a cost analysis (GIA, storey count, tendering method, location, base date, specification outline).
- BCIS Tender Price Index (TPI): adjustment from the BCIS data base date to the current base date, calculated as: ((current TPI − base TPI) ÷ base TPI) × 100%. BCIS publishes quarterly TPI values and forecasts.
- BCIS Location Factors: regional tender price indices used to adjust BCIS benchmark data to the project location. London factor is typically the highest; North East and Wales among the lowest.
- ICMS (International Construction Measurement Standards): RICS Cost Prediction Professional Statement recommends ICMS reporting format where in the client's best interests, particularly for international or public sector projects.
Practical Application
Common Mistakes to Avoid
- Omitting the cost movement schedule from the Cost Plan 2 report — under RICS Cost Prediction (2021), stating the change from the previous cost plan with reasons is a mandatory professional obligation.
- Maintaining Stage 2 contingency (10–15%) without justification — if design is sufficiently developed to reduce contingency, carrying an inflated rate misleads the client about true design cost.
- Applying TPI without documenting base date, current date and TPI values used — the BCIS adjustment must be transparent and auditable; an undocumented TPI uplift cannot be defended at audit.
- Using NIA instead of GIFA for elemental unit rate calculations — all BCIS benchmark rates and NRM 1 rules are based on GIFA; substituting NIA overstates EURs and produces an incorrect benchmark comparison.
- Issuing CP2 from partially coordinated information — a cost plan is only as reliable as the information on which it is based; the design team's information status must be documented as a qualification.
- Combining risk allowance and design contingency into a single 'contingency' line — these provisions have different derivations and purposes; presenting them as one sum prevents effective cost management.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Design Economics & Cost Planning (L2) | Procurement & Tendering (L1) | Programming & Planning (L1)
Cost Plan 2 Checklist
CPD Learning Outcomes
- Prepare Formal Cost Plan 2 at RIBA Stage 3 using NRM 1 Part 3/4 measurement rules, applying BCIS TPI and location adjustments and benchmarking elemental unit rates against BCIS cost analysis data.
- Prepare a cost movement schedule reconciling Cost Plan 2 to Cost Plan 1, categorising each variance by type, in compliance with the mandatory requirements of RICS Cost Prediction (Professional Statement, 2021).
- Apply the appropriate Stage 3 design contingency rate (5–10%) and explain the reduction from Stage 2 (10–15%) in terms of design development and reduced uncertainty.
Further Reading
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012, RICS Books) — Parts 3 and 4
- RICS Cost Prediction (Professional Statement, 1st edition, effective 1 July 2021, RICS)
- RICS Cost Analysis and Benchmarking (2nd edition, 2024, RICS)
- BCIS Online Cost Information Service — Tender Price Index, Location Factors, Cost Analyses (BCIS)
- RICS Quantity Surveying and Construction Professional Statement (2021, RICS)
- ICMS: International Construction Measurement Standards (2nd edition, 2019, ICMS Coalition)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.