Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
The Stage 3 Updated Cash Flow Forecast refreshes the indicative Stage 2 forecast using the Cost Plan 2 budget, a developed construction programme, and confirmed inflation adjustments — principally BCIS Tender Price Index (TPI) for tender inflation and a construction inflation allowance for the construction period. By Stage 3, the construction programme should reflect coordinated sequencing information from the architect, structural engineer and M&E engineer, producing a materially more reliable spend profile than the Stage 2 indicative forecast.
Two distinct inflation allowances are required at Stage 3 and must be separately identified within both Cost Plan 2 and the Cash Flow Forecast: tender inflation (the movement in construction prices from the cost plan base date to the anticipated tender return date) and construction inflation (the movement from the tender return date to the mid-point of the construction period). Both are calculated using the BCIS TPI formula: ((current index − base index) ÷ base index) × 100%.
The Stage 3 Cash Flow Forecast is the last version produced before procurement commences. It informs the client's funding drawdown arrangements, bank covenant reporting, and funder's cash flow requirements. The QS must ensure it is comprehensive, clearly states all assumptions, and distinguishes between the construction cost cash flow and the all-in project cash flow (including professional fees, statutory charges and client direct costs).
Key Principles
- RICS Cash Flow Forecasting (RICS guidance note, 2014): the principal RICS framework for construction project cash flow preparation, including S-curve methodology, fee phasing, retention modelling and inflation treatment.
- NRM 1 (2nd edition, 2012): Cost Plan 2 provides the total project budget and elemental breakdown that forms the basis of the Stage 3 forecast; inflation allowances must follow NRM 1 guidance on tender and construction inflation.
- BCIS Tender Price Index (TPI): BCIS publishes quarterly TPI values and forecasts. Tender inflation formula (from NRM 1 / APC study packs): ((current TPI − base TPI) ÷ base TPI) × 100%.
- BCIS Duration Calculator: BCIS tool that estimates construction duration from project value, building function, procurement route and selection method — used where a confirmed programme is not yet available.
- RICS Cost Prediction (Professional Statement, 1st edition, 2021): requires the cash flow to state its base date, inflation assumptions and reasons for change from the previous forecast.
- JCT Standard Building Contract (SBC/Q, 2016 edition), Clauses 4.9–4.13: interim payment and retention provisions — contextual basis for modelling monthly valuations, retention deductions and releases in the cash flow.
Practical Application
Common Mistakes to Avoid
- Applying a single inflation allowance instead of separating tender inflation (base date to tender return) and construction inflation (tender return to construction mid-point) — NRM 1 and the BCIS methodology require these to be identified separately.
- Using a linear (even-spread) spend profile at Stage 3 — by this stage, sufficient programme information exists to produce a properly phased S-curve; a linear profile would misrepresent the client's drawdown requirements.
- Presenting only the construction cash flow without the all-in project cash flow — the client's funder typically requires the full project spend profile including fees, statutory charges and client direct costs.
- Failing to update the cash flow when the programme or Cost Plan 2 budget changes — the cash flow is a live document; any change to programme dates or construction budget must trigger an immediate update.
- Not stating the TPI values and base dates used for inflation calculations — an undocumented inflation adjustment cannot be audited or reconciled at later stages.
- Ignoring the effect of retention timing on the client's net cash flow — retention release at PC and DLP end are significant cash receipts that must be correctly timed in the forecast.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Programming & Planning (L1) | Commercial Management (L1) | Design Economics & Cost Planning (L2)
Cash Flow Forecasting Checklist
CPD Learning Outcomes
- Calculate and separately identify tender inflation and construction inflation in a Stage 3 cash flow forecast using the BCIS TPI formula and BCIS published/forecast index values.
- Prepare an updated project cash flow forecast using S-curve methodology with element-specific phasing, retention modelling and professional fee phasing, producing both a construction cost cash flow and an all-in project cash flow.
- Advise clients on the evolution of cash flow accuracy from the Stage 2 indicative forecast to the Stage 3 updated forecast, and the basis on which the Stage 4 contract-based forecast will supersede it.
Further Reading
- RICS Cash Flow Forecasting (RICS guidance note, 2014, RICS Books)
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012, RICS Books)
- BCIS Online — Tender Price Index, Cost Forecasting Service and Duration Calculator (BCIS)
- RICS Cost Prediction (Professional Statement, 1st edition, effective 1 July 2021, RICS)
- JCT Standard Building Contract with Quantities (SBC/Q, 2016 edition) — Clauses 4.9–4.13
- HM Revenue & Customs: VAT Notice 708 — Buildings and Construction (current edition, HMRC)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.