Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
A Contract Sum Analysis (CSA) is the pricing document used in Design and Build contracts in place of a Bill of Quantities. Submitted by the contractor as part of their Contractor's Proposals in response to the Employer's Requirements, the CSA breaks down the lump-sum contract price into elements or components, enabling the employer's agent to assess interim payment applications, value employer-instructed changes, and audit the reasonableness of the contractor's pricing build-up.
Under the JCT Design and Build Contract (DB 2016), the CSA is a contract document. Its format must be specified by the employer in the Employer's Requirements — if the employer does not prescribe the CSA format, the contractor may submit it in any format they choose, which may not support effective post-contract cost management. The employer's agent (typically the QS) should specify the required CSA structure in the Employer's Requirements before tenders are issued.
For NEC4 contracts under Option A (Priced Contract with Activity Schedule), the equivalent document is the Activity Schedule — a list of activities with associated prices. Under NEC4 Option B (Priced Contract with Bill of Quantities), a traditional BQ is used. The QS must confirm which NEC4 option applies and prepare the appropriate pricing document accordingly.
Key Principles
- JCT Design and Build Contract (DB 2016): the CSA is a Schedule to the Contract and a contract document; it governs the basis for interim payment (valued against completed CSA elements) and the calculation of the adjusted contract sum following employer changes.
- RICS Employer's Agent: Design and Build (1st edition, 2017, effective January 2018): the employer's agent is responsible for reviewing the CSA submitted with Contractor's Proposals, assessing its completeness, and using it as the basis for post-contract payment assessment and change valuation.
- NRM 1: RICS New Rules of Measurement (2nd edition, 2012): even for D&B contracts, RICS recommends structuring the CSA using NRM 1 Group Elements to facilitate benchmarking and cost management; some employers specify an NRM 1-structured CSA in the Employer's Requirements.
- RICS Developing a Construction Procurement Strategy (2nd edition, 2024): confirms that under D&B procurement, the employer commits to a concept design at an early stage; the CSA must reflect the full scope of the Employer's Requirements, including all CDP obligations.
- NEC4 Engineering and Construction Contract (2017) — Options A and B: Activity Schedule (Option A) is the nearest NEC4 equivalent to a CSA; BOQ (Option B) uses NRM 2 measurement rules.
Practical Application
Common Mistakes to Avoid
- Not prescribing the CSA format in the Employer's Requirements — without a specified format, the contractor may submit an insufficiently detailed or non-standard breakdown that makes post-contract cost management difficult.
- Accepting a CSA that does not reconcile to the Form of Tender lump sum — any discrepancy between the CSA total and the Form of Tender must be resolved before contract execution; a discrepancy creates ambiguity about the contract sum.
- Not checking the CSA against the full scope of the Employer's Requirements — items in the ER that are not reflected in the CSA are not priced; claiming them as employer-instructed changes post-contract will be contested by the contractor.
- Using the CSA for change valuation without confirming the element rates are reasonable — a contractor who has under-priced an element in the CSA will resist using those rates for additions; over-priced elements will be used by the contractor to their advantage.
- Not updating the CSA schedule during the contract to reflect agreed changes — a CSA that does not reflect the current adjusted contract sum becomes unreliable as a management tool.
- Unilaterally adjusting the contract total to correct arithmetic errors in the priced document — under most contract forms the default rule preserves the tender total and adjusts individual rates. Changing the total without the tenderer's written agreement creates a dispute over the contract sum and may invalidate the award.
APC Competency & Quick Reference
APC Competencies: Procurement & Tendering (L2) | Cost Management (L2) | Commercial Management (L2) | Design Economics & Cost Planning (L1)
Contract Sum Analysis Checklist
CPD Learning Outcomes
- Specify an appropriate Contract Sum Analysis format in Employer's Requirements, review a CSA submitted with Contractor's Proposals, and identify discrepancies requiring resolution before contract execution.
- Apply a CSA for interim payment assessment under JCT DB 2016 (percentage complete × element value) and for change valuation, and distinguish this approach from BQ-based interim valuation under JCT SBC/Q.
- Compare the Contract Sum Analysis (JCT DB) with the NEC4 Activity Schedule (Option A) in terms of format, payment mechanism and cash flow implications.
Further Reading
- JCT Design and Build Contract (DB, 2016 edition, Sweet & Maxwell)
- RICS Employer's Agent: Design and Build (1st edition, 2017, RICS Books)
- RICS Developing a Construction Procurement Strategy (2nd edition, 2024, RICS)
- RICS NRM 1: Order of Cost Estimating and Cost Planning (2nd edition, 2012, RICS Books) — Group Element structure
- NEC4 Engineering and Construction Contract (2017, Thomas Telford) — Options A and B
- RICS Appropriate Contract Selection (2nd edition, 2024, RICS)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.