Purpose
Note on JCT editions: JCT has published the 2024 Edition. This guidance cites JCT SBC/Q 2016 clause references; the commercial and payment mechanisms are substantively unchanged in the 2024 edition, but specific clause references should be verified against the contract edition in use on any given project.
The contractor's preliminaries submission and pricing schedule require careful review and finalisation before the contract is executed. Preliminaries represent the contractor's allowances for site establishment, management, temporary works, plant, welfare, insurance and time-related costs — typically 12–18% of the measured works value. Understanding the contractor's preliminaries build-up is essential for the QS: it reveals the contractor's programming assumptions, management team quality, and the fixed/time-related split that governs how preliminaries are valued in the event of programme extensions or contractor delay.
This note sits immediately before Contract Document Preparation (GN-TD-12) because the pricing schedule — whether a Bill of Quantities, Contract Sum Analysis or Activity Schedule — must be fully reviewed, agreed and finalised before the contract is executed. Any qualifications, provisional entries or discrepancies in the pricing document must be resolved at this stage, as the pricing document forms a contract document and cannot be unilaterally amended post-execution without a formal change instruction. Finalising the pricing schedule first ensures that the contract sum, preliminaries breakdown and pricing document are complete and consistent before the contract documents are assembled.
NRM 2 (2nd edition, 2021) provides the standard framework for preliminaries items. RICS Cash Flow Forecasting (2nd edition, 2024) confirms that the contractor's preliminaries split (fixed vs time-related) is a key input to the Stage 5 cash flow forecast and interim payment assessment.
Key Principles
- NRM 2 (2nd edition, 2021), Section 1 — Preliminaries: defines the structure for BQ preliminaries — project/site overview, employer's requirements, main contractor's cost items (fixed charges, time-related charges, method-related charges).
- RICS Cash Flow Forecasting (2nd edition, 2024), Section 3 — Practical Application: the contractor's fixed/time-related preliminaries split is used to model how preliminary costs are phased in the cash flow forecast; fixed charges are front-loaded; time-related charges are spread over the programme.
- RICS Tendering Strategies (1st edition, 2015), Section 3.10: overheads and profit should be submitted as separate percentages (not combined); the tender analysis should examine whether OH&P percentages are reasonable relative to current market conditions.
- JCT SBC/Q 2016, Schedule 2 — Contractor's Designed Portion: where a CDP is included, the pricing schedule must include the CDP design fee and the CDP construction cost as separately identifiable items.
- Construction (Design and Management) Regulations 2015: the contractor's preliminaries must include adequate allowance for CDM compliance — welfare facilities, health and safety management, notification of HSE (F10) — as specified in the pre-construction information.
Practical Application
Common Mistakes to Avoid
- Not reviewing the fixed/time-related preliminaries split before contract execution — without this information, the QS cannot correctly value preliminary costs in interim payment certificates or in the event of an extension of time.
- Accepting combined overheads and profit as a single percentage — combined OH&P prevents the QS from assessing the contractor's profit margin independently; RICS Tendering Strategies (2015) recommends they are stated separately.
- Overlooking front-end loading in the pricing schedule — front-end loading inflates early interim payments and effectively provides the contractor with an advance payment that is not secured by retention.
- Not confirming addendum compliance in the pricing schedule — missing addendum items will result in disputes when those items arise for payment during the construction phase.
- Proceeding to contract document assembly (GN-TD-12) before the pricing schedule is fully finalised and agreed — any discrepancy discovered post-execution cannot be corrected without a formal change instruction.
APC Competency & Quick Reference
APC Competencies: Cost Management (L2) | Commercial Management (L2) | Procurement & Tendering (L1) | Contract Administration (L1)
Prelims & Pricing Schedule Checklist
CPD Learning Outcomes
- Review a contractor's preliminaries submission, confirm the fixed/time-related split, and explain how this split affects interim payment assessment and the valuation of extensions of time.
- Identify front-end loading in a contractor's pricing schedule and advise the client on its implications for payment security and contractor insolvency risk.
- Confirm that overheads, profit, daywork percentages and provisional sum/PC sum allowances in the pricing schedule are reasonable, correctly structured, and fully agreed before the pricing schedule is incorporated into the contract documents.
Further Reading
- RICS NRM 2: Detailed Measurement for Building Works (2nd edition, 2021, RICS Books) — Section 1 (Preliminaries)
- RICS Cash Flow Forecasting (2nd edition, 2024, RICS) — Section 3
- RICS Tendering Strategies (1st edition, 2015, RICS Books) — Section 3.10
- RICS Schedule of Basic Plant Charges (current edition, RICS)
- JCT Standard Building Contract with Quantities (SBC/Q, 2016 edition, Sweet & Maxwell)
- Construction (Design and Management) Regulations 2015 (SI 2015/51, HMSO)
Sections 3–8 are for subscribers
Your subscription unlocks Practical Application steps, Common Mistakes to Avoid, APC Quick Reference, the Stage Checklist, CPD Learning Outcomes, Further Reading, and all production-ready templates.